Fence Ledger
Rail stock is the item people most often underbuy, because it is easy to work out from the fence length and easy to get wrong by one whole multiple.
3 per section across 13 sections, plus a 10% waste allowance.
The trap is multiplying the fence length by the rails per section instead of multiplying the section count by it. Those are different numbers whenever the run does not divide evenly by the post spacing, and they diverge further the more corners and gates the fence has, because each forced post adds a section boundary. Count sections first, then rails.
Every assumption above is editable. Change the length, the spacing, the hole size — the numbers and the working update as you go.
These are typical values, not requirements. Post depth in particular is governed by your local frost line and building code — check before you dig.
National planning ranges compiled from published US construction cost guides, last checked September 2026 (confidence: medium-low). Prices vary sharply by region, season and contractor. These are estimates for planning, not quotes.
Sources: homeguide.com, calcsummit.com, angi.com, ergeon.com, homewyse.com
| Material | Size | Quantity |
|---|---|---|
| Posts | 4x4 | 14 |
| Rails incl. waste | 2x4 | 40 |
| Pickets incl. waste | 1x6 | 222 |
| Concrete mix | 24bags | |
| Gravel | 6bags | |
| Exterior screws | ≈1,500 | |
| Walk gate kit | 1 |